TL;DR
Wallonia ordered Google to stop construction on a building at its planned Farciennes data centre, saying the three-hectare structure lacked proper planning permission. Google says work is paused and it will comply with local laws; the company has challenged a separate refusal to change the project’s cooling plan, with a court hearing scheduled for January.
Wallonia’s regional authorities have ordered Google to halt construction on a building at its planned data centre in Farciennes, Belgium, saying the three-hectare structure was built without proper planning permission. Google says it has paused work while awaiting further guidance. The order places a local permitting dispute over a major technology project in the spotlight, as the company also contests a refusal to change the site’s cooling system.
Regional officials said inspectors visited the site on Thursday and instructed Google representatives to stop construction. Nicolas Yernaux, a spokesman for Wallonia’s authorities, described the matter to AFP as a “major offense,” alleging that a building covering three hectares had been constructed without the required permission. AFP’s report was published by Arab News on November 27. The regional authorities’ account establishes the reason they gave for the order; the order itself was not available online in the source reporting.
The dispute concerns one building, not the entire data centre site. The project is on a former mining property covering about 50 hectares, according to AFP. Google told the BBC that it had paused work in Farciennes “pending additional guidance” and said it remained “committed to complying with local laws.” The company has not, in the material available, publicly accepted the authorities’ allegation that the building lacked permission.
A separate issue involves the project’s proposed cooling method. The original plan specified air cooling, according to Belgian media cited by AFP. Google later sought permission to use water from the nearby River Sambre instead. Regional authorities rejected that application over the summer, with concerns about water use heightened by severe drought conditions since spring, AFP reported. Greenpeace Belgium said this week that drone footage showed work continuing after the relevant planning permission was revoked in August. That is the group’s account; it is not a court finding.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Permits Put Data Centre Plans on Hold
The order illustrates how planning permission and access to resources can affect data centre construction, alongside the availability of land, electricity and computing equipment. A halt to work on one building does not establish that the whole Farciennes project is cancelled, but it can delay construction while the permit dispute is addressed.
The cooling application adds a local resource question to the planning dispute. Data centres generate heat and require cooling, but the reports cited here do not state how much water Google proposed to draw from the Sambre or what the project’s total water needs would be. With authorities citing drought concerns in rejecting the change, the case shows how a proposed technical adjustment can become a contested permitting issue.
For residents, the immediate development is a regional order affecting work at a nearby site. For suppliers and customers of cloud and AI services, the episode is a reminder that local approvals can shape when new capacity becomes available. No delay to a specific service or customer has been reported in the source material.
Popular right now

Ninja CREAMi Scoop & Swirl 13-in-1 Ice Cream and Soft Serve Maker, NC701

Dyson Airwrap Multi-Styler Complete Long

Dyson Cyclone V10 Origin Cordless Vacuum
As an affiliate, we earn on qualifying purchases.
Farciennes Cooling Plan Dispute
The Farciennes site is planned on a former mining property in southern Belgium. The disputed building covers three hectares, roughly four football pitches, while the wider property spans about 50 hectares, AFP reported. That difference matters: the current order concerns a particular structure and should not be described as a shutdown of every planned facility on the site.
The planning issue and the cooling dispute are related but distinct. Authorities refused Google’s request to change the cooling plan from air to water drawn from the Sambre over the summer. Greenpeace Belgium said the latest version of the permission had been revoked in August and alleged that construction continued afterward. Regional officials subsequently ordered a halt, according to AFP. The sequence is reported, but the source material does not provide the full permit record or the legal reasoning behind each decision.
Farciennes is not the only location where Google’s data centre construction has faced a stop. AFP reported that Finnish authorities halted work at two Google data centre sites in October. The BBC, citing Data Center Map, reported that Belgium had 54 data centres and that about 13,500 existed worldwide. Those figures provide scale; they do not establish that the separate cases have the same cause or outcome.
“We have operated in Belgium for over 15 years and remain committed to complying with local laws.”
— Google, in a statement reported by the BBC
Permit Case Still Unresolved
The available reporting does not include the written stop-work order or the full planning documents, so the exact scope, conditions and legal basis of the order cannot be independently detailed here. It is also unclear whether the disputed building can later be regularised or whether construction can resume after additional approvals.
Google has challenged the regional refusal of its water-cooling application, but the source material does not give the company’s legal arguments or the authorities’ full response. Reports do not specify the proposed water volume, the project’s overall water demand, or the timetable for resolving the separate construction-permission allegation. Greenpeace’s claim that work continued after permission was revoked has not been presented as a court-established fact.
January Hearing and Site Guidance
A court hearing on Google’s challenge to the refusal of its cooling-plan application is scheduled for January, AFP reported. The outcome could clarify whether the company may pursue the proposed use of water from the Sambre, but it should not be assumed to settle every planning issue at the site.
For now, Google says construction is paused pending additional guidance, and the regional stop-work order remains the reported position. The next developments to watch are the court hearing, any further direction from Wallonia’s authorities, and whether the company seeks or receives permission to continue work on the affected building. The timing and conditions for any restart have not been announced in the source material.
Key Questions
Why did Wallonia order Google to stop construction?
Regional authorities said a three-hectare building was constructed without proper planning permission. The allegation has not been resolved in court in the reporting available.
Has Google stopped all work at the Farciennes site?
The order concerns one building, not the whole planned site. Google told the BBC that it had paused work in Farciennes pending further guidance.
What is the dispute about the River Sambre?
Google sought to change the project’s cooling plan from air cooling to using water from the nearby River Sambre. Regional authorities refused the application over the summer, citing concerns that included drought conditions, AFP reported.
When will the legal dispute be heard?
AFP reported that a court hearing on Google’s challenge to the cooling-plan refusal is scheduled for January. The source material does not give a specific hearing date or say when construction could resume.
Source: ThorstenMeyerAI.com